Monday, July 12, 2010

Brandon Auditorium Restoration July 12th


Brandon MN
Work is being done to repair and update the sewer connections.
The workers are also demolishing the old unused water cistern which was located under the front sidewalk. This is being done to help eliminate unwanted basement moisture.

Brandon Auditorium Restoration July 9th


Brandon MN
Repairs to the chimney have begun.

Tuesday, July 6, 2010

Brandon Auditorium Restoration July 6, 2010

Brandon MN
A worker from the Building Restoration Corporation of Minneapolis is removing the old cracked and crumbling mortar from around the windows and between the rocks.











Tuesday, June 22, 2010

Brandon Auditorium Restoration June 22, 2010







Brandon MN
Building Restoration Corp. is busy removeing the metal signs from the building and power washing the exterior.

Sunday, June 20, 2010

Brandon Auditorium Restoration Begins June 14

Brandon MN
Excitement is in the air at 105 Holmes Avenue in the City of Brandon!

At the June meeting, the City Council awarded contracts for the restoration:
Concrete - Bitzan-Ohren
Masonry - Building Restoration Corp.
Carpentry - BCS, Inc.
Roofing - Membrane Roofing -
Roof I
Finishes - Beers Painting
Electrical - Lennes Bros.
Total projected cost for Phase I - $254,390.
Renovations began Monday, June 14, 2010. As we all know, 75 years have taken a huge toll on the building, and the need to make repairs is apparent. Fundraising efforts by the community and funds appropriated by the City of Brandon have made it possible to begin Phase I of the project. Phase I is expected to be finished in time for our Summerfest. You will be able to follow the progress of the project on the ORB Management web site at: http://orbmanagement.biz/agree.html with the following username and password. Username: BrandonAud Password: remodel$ Above you can see that the concrete sidewalks have been removed. Below is BCS, Inc. in the process of demolishing the east entrance to the current History Center(old Fire Hall/City Hall entrance) which will be totally restored to its original design.



Original Brandon Auditorium 1936


Brandon MN
The original Brandon Auditorium was completed in 1936 and included the Brandon Fire Department Fire Hall.
Notice the four white doors and the small windows.