Brandon MNExcitement is in the air at 105 Holmes Avenue in the City of Brandon!
At the June meeting, the City Council awarded contracts for the restoration:
Concrete -
Bitzan-
OhrenMasonry - Building Restoration Corp.
Carpentry -
BCS, Inc.
Roofing - Membrane Roofing -
Roof I
Finishes - Beers Painting
Electrical -
Lennes Bros.
Total projected cost for Phase I - $254,390.
Renovations began Monday, June 14, 2010. As we all know, 75 years have taken a huge toll on the building, and the need to make repairs is apparent. Fundraising efforts by the community and funds appropriated by the City of Brandon have made it possible to begin Phase I of the project. Phase I is expected to be finished in time for our
Summerfest. You will be able to follow the progress of the project on the ORB Management web site at:
http://orbmanagement.biz/agree.html with the
following username and password.
Username:
BrandonAud Password: remodel$ Above you can see that the concrete sidewalks have been removed. Below is
BCS, Inc. in the process of demolishing the east entrance to the current History Center(old
Fire Hall/City Hall entrance) which will be totally restored to its original design.